IADA, Parit 2 1/2 Barat, Panchang Bedena, Sungai Besar, Selangor

Date: 14/06/2015
CC Type: CC5 (Batch Roll)
Layup : Longitudinal Layers
Quantity: 160m²
Location: IADA, Parit 2 1/2 Barat, Panchang Bedena,
Sungai Besar, Selangor

CC was used to lined an irrigation channel and a sump. The installation work was completed in one day excluding the excavation of the channel which took one day.

Project Gallery